St. Louis Park, Minnesota Logo

(952) 924-2555

rss feed city map facebook facebook youtube vimeo twitter facebook

  
printer friendly versionContact by Phone (952) 924-2555

Construction Projects

sort: title | date
 

Current & Future Projects

updated: Tuesday, March 26, 2013

Projects Under Construction

Future Projects



Recently Completed Projects

updated: Tuesday, May 07, 2013

2012 Projects

2011 Projects

 



Construction Bids

updated: Tuesday, May 21, 2013

As required by state law, the City of St. Louis Parks Public Works Department uses the competitive-bidding process for certain contracts estimated to cost over $100,000. Generally, the competitive-bidding process involves publication of an advertisement to solicit sealed bids and an award of the contract to the "lowest responsible bidder"...


2013 Local Street Rehabilitation

updated: Friday, May 10, 2013

Prior to the street work, the gas company, CenterPoint Energy, will replace the gas mains and service lines throughout the project area. This work is scheduled to begin in mid-May. Crews will first install the new gas mains in the boulevard area along the streets. Then a second crew will come in after the gas main work has been completed to install...


France Avenue Pedestrian Improvements 26th Street to 22nd Street

updated: Tuesday, March 26, 2013

The City is planning improvements along France Avenue from 26th Street up to 22nd Street in Minneapolis for 2013. This work is expected to include a 6 foot boulevard style concrete sidewalk on the west side of France Avenue from 26th Street to 22nd Street, roadway narrowing along the west side, lane narrowing for north and south bound traffic, narrow...


Highway 100 Reconstruction

updated: Friday, April 19, 2013

MnDOT submitted a formal request to the City for project municipal consent. A public hearing was held by the City Council on Nov. 5, 2012 to consider the request and receive public comment. The Council discussed the request further at a study session on November 19. At the regular City Council meeting on December 3,...


Highway 7 & Louisiana Avenue Interchange

updated: Friday, May 17, 2013

Although work on the Interchange project won’t begin until late May or early June, private utilities are now working to relocate their facilities before the start of road construction. Xcel Energy is currently working to place the overhead power lines along Highway 7 and along Lake Street near Louisiana Avenue below ground. Construction of...


Minnetonka Blvd Improvements (In Minnetonka to Hwy 169)

updated: Friday, April 19, 2013

Current Status
The project is essentially complete. However, a final inspection of the project has been completed and the Contractor has been working to finish up miscellaneous warranty items.

For additional information on the project visit the City of Minnetonka’s project website or contact the Project Engineer, Nate Stanley.

Project Description
The City of Minnetonka is constructing a trail along the south side of Minnetonka Boulevard from Oakridge Road to just east of Hwy 169 and converting Minnetonka Boulevard from a 4 lane section to a 3 lane section.

The trail will extent under Hwy 169 and connect with the existing paved trail in St. Louis Park. The roadway will remain open to traffic throughout the duration of the project; however lane closures or lane shifts will be required to facilitate the construction

Contact
Nate Stanley | Project Engineer
City of Minnetonka |14600 Minnetonka Blvd. | Minnetonka, MN 55345
P: (952) 939-8238 | F: (952) 939-8244 | nstanley@minnetonka.com

Jack Sullivan | Engineering Project Manager
City Hall | 5005 Minnetonka Blvd. | St. Louis Park, MN 55416
P: (952) 924-2691 | F: (952) 924-2663 | jsullivan@stlouispark.org



Park Center Blvd Traffic Signal

updated: Friday, April 19, 2013

Current Status
The Park Center Boulevard is essentially complete. There are a few remaining pavement markings and some landscaping work that will be completed in the spring of 2013.

Project Description
A traffic signal will be installed on Park Center Boulevard just south of 36th Street at the Target Store and Park Summit entrances. The signal will consolidate the east entrance to the Target Store and the entrance into the new Park Summit development, now under construction.

The roadway will remain open to traffic, however lane closures are to be expected. The construction will be completed in five phases to maintain access to the businesses along Park Center Boulevard. The project is expected to be completed late this fall.

Contact
Jack Sullivan | Engineering Project Manager
City Hall | 5005 Minnetonka Blvd. | St. Louis Park, MN 55416
P: (952) 924-2691 | F: (952) 924-2663 | jsullivan@stlouispark.org



Sanitary Sewer Rehabilitation - Local Streets

updated: Friday, April 05, 2013

The City is undertaking a project to rehabilitate the sanitary sewer pipe that is located beneath selected streets in the Oak Hill, Brookside and Browndale Neighborhoods. The City contractor, Insituform Technologies USA, will begin the rehabilitation work the week of January 14, 2013. In early December, the contractor performed preliminary work cleaning...


Sanitary Sewer Rehabilitation - Regional (Metropolitan Council)

updated: Monday, April 29, 2013

Metropolitan Council Environmental Services (MCES), the operator of the metro-area wastewater collection and treatment system, and its contractor, Lametti & Son’s, have been replacing the regional sanitary sewer pipe in Minneapolis (Cedar-Isles, Dean Neighborhoods) and are steadily working west toward St. Louis Park. The overall project...


Street Light Replacement Program

updated: Wednesday, May 01, 2013

The Street Light Replacement Program is a long term program providing for the replacement of street light systems which have reached their life expectancy. The street lights proposed for replacement in 2013 are along both sides of Cedar Lake Road from Highway 169 to Louisiana Avenue. Both the poles and the light fixtures will be replaced as part of...


Traffic Signal Painting

updated: Tuesday, May 14, 2013

Traffic Signal Painting is a multi-year program that provides for the painting of the 38 traffic signals for which the City has maintenance responsibility. The city typically paints two signal systems each year. The signals proposed for painting in 2013 are at the intersections of Park Place Boulevard & 16th Street and at Zarthan Avenue and 16th...


West 44th Street Reconstruction

updated: Friday, April 19, 2013

The reconstruction of 44th Street from Brookside Avenue to France Avenue is being administered by the City of Edina with the support of the City of St. Louis Park. Reconstruction will consist of the removal and replacement of the existing asphalt pavement, curb and gutter, and utility and drainage improvements. Consideration in maintaining the existing...


Hennepin County Construction Projects

updated: Friday, April 05, 2013

Visit Hennepin County's web site to learn about county roadway construction projects.



MnDOT Construction Projects

updated: Friday, February 15, 2013

Visit the Minnesota Department of Transportation's web site to learn about highway construction projects.



More Links

Public Works MSC
7305 Oxford Street
St. Louis Park, MN 55426
Phone: (952) 924-2555 Email: info@stlouispark.org