St. Louis Park, Minnesota Logo

(952) 924-2656

rss feed city map facebook facebook youtube vimeo twitter facebook

  
printer friendly versionContact by Phone (952) 924-2656

Construction Projects

sort: title | date
 

Current & Future Projects

updated: Wednesday, April 23, 2014

Projects Under Construction

Future Projects



Recently Completed Projects

updated: Wednesday, April 23, 2014

2013 Projects

2012 Projects

2011 Projects



Construction Bids

updated: Friday, February 28, 2014

As required by state law, the City of St. Louis Parks Engineering Department uses the competitive-bidding process for certain contracts estimated to cost over $100,000. Generally, the competitive-bidding process involves publication of an advertisement to solicit sealed bids and an award of the contract to the "lowest responsible bidder"...


2013 Local Street Rehabilitation

updated: Monday, December 23, 2013

The city awarded the 2013 Local Street Rehabilitation Project to Astech Construction. Construction for this project has been substantially completed with only minor repair items, site cleanup, and final acceptance of the turf establishment remaining. The method of turf restoration that was used is called hydroseeding. Hydroseeding is a process by which...


2013 MSA Street Rehabiliation - Parkdale Drive

updated: Monday, December 09, 2013

The project will be constructed under traffic. However, there may be temporary nighttime closures. Motorists will be guided through the work zone during the periods of temporary lane closures. Temporary traffic lane closures will occur next to work areas resulting in single lane traffic in each direction. Access to driveway entrances and intersections...


2013 Street Sealcoating

updated: Tuesday, April 01, 2014

This year’s sealcoat project covered the southwest portion of the city, including the Aquila, Minnehaha, and Cobblecrest Neighborhoods (see map). The contractor finished the sealcoating operations on Wednesday, August 7 and the city has completed the final sweeping operations. The city has completed a temporary restoration of the Gorham...


2013-14 Sanitary Sewer Rehabilitation - Local Streets

updated: Tuesday, April 01, 2014

The city is undertaking a project to rehabilitate the sanitary sewer pipe that is located beneath selected streets in the Oak Hill, Cedar Manor and Lenox Neighborhoods. Our contractor, Visu-Sewer Incorporated, will begin the rehabilitation work the week of April 14, 2014. In March, the contractor performed preliminary work cleaning the sewer pipe in...


2014 Local Street Rehabilitation

updated: Monday, March 10, 2014

Current Status
The city has commenced the preliminary design for the 2014 Local Street Rehabilitation. In order to speed up construction next spring, Centerpoint Energy will be installing gas mains this fall. They are planning to install the mains starting the week of October 7. Work should take about three weeks.

Project Description
Each year the city rehabilitates several miles of local residential streets. For the 2014 project, the streets to be rehabilitated are located primarily in the Browndale Neighborhood, with some work occurring in the Minikahda Vista and Triangle Neighborhoods (see map).

Street rehabilitation work generally consists of removing and replacing the existing bituminous pavement and replacing portions of concrete curb and gutter as needed. Other work includes storm sewer and watermain repairs. Access to properties is typically maintained throughout construction.

Streets to be chipsealed in this area will be done during 2018.

Resources
06-20-2013 Residential Survey Notice Letter
06-20-2013 Project Location Map

Contact
Jack Sullivan | Engineering Project Manager
City Hall | 5005 Minnetonka Blvd. | St. Louis Park, MN 55416
P: (952) 924-2691 | jsullivan@stlouispark.org



2014 MSA Project: Pennsylvania Avenue Street Improvements from Wayzata Blvd. to Franklin Ave.

updated: Friday, February 21, 2014

Pennsylvania Avenue is a Municipal State Aid (MSA) street. The funding for this street will be paid for with money allocated by the State to St. Louis Park. In order to use the funds, the road must meet MSA standards. For on street parking on one side, the road must be at least 32 feet in width. The majority of the street is 32...


CSAH 25 Resurfacing (France Avenue to Hwy 100)

updated: Wednesday, January 22, 2014

Hennepin County will be performing a mill and overlay (resurfacing) of CSAH 25 between Highway 100 and France Avenue. Essentially, the existing pavement surface will be removed and replaced. CenterPoint Energy or other utility companies may be performing underground utility work prior to the paving operation. Expect periodic lane closures...


France Avenue Pedestrian Improvements 26th Street to 22nd Street

updated: Friday, December 20, 2013

The city is planning improvements along France Avenue from 26th Street up to 22nd Street in Minneapolis. This work includes a 6 foot boulevard style concrete sidewalk on the west side of France Avenue from 26th Street to 22nd Street, roadway narrowing along the west side, lane narrowing for north and south bound traffic, narrow striped shoulders...


Highway 100 Reconstruction

updated: Wednesday, February 26, 2014

Beginning in late summer 2014, MnDOT will start construction on TH100 from just north of W. 36th Street to W. 26th Street. This is a multi-year project that will be completed in the fall of 2016. The estimated cost is $60 million. In conjunction with the road work, the city will be replacing the water, sanitary and storm utilities that cross under...


Highway 7 & Louisiana Avenue Interchange

updated: Wednesday, April 23, 2014

As of March 24, C.S. McCrossan Construction, Inc. began occasionally starting work at 6 a.m. on the weekdays and at 7 a.m. on Saturdays. These extra hours will continue through November 2014. Note: pile driving will not begin before 7 a.m. After the unseasonably cold and snowy winter, crews will need the extra hours and Saturdays to complete...


Park Center Blvd Traffic Signal

updated: Monday, April 07, 2014

Current Status
This project has been completed. If you have any questions or comments about the project please contact the Engineering Department.

Project Description

A traffic signal will be installed on Park Center Boulevard just south of 36th Street at the Target Store and Park Summit entrances. The signal will consolidate the east entrance to the Target Store and the entrance into the new Park Summit development, now under construction. 

The construction will be completed in five phases to maintain access to the businesses along Park Center Boulevard. The project is expected to be completed late this fall.

Contact
Jack Sullivan | Engineering Project Manager
City Hall | 5005 Minnetonka Blvd. | St. Louis Park, MN 55416
P: (952) 924-2691 | F: (952) 924-2662 | jsullivan@stlouispark.org



Random Concrete Repairs

updated: Monday, December 23, 2013

Current Status
The contractor has completed all work associated with the 2013 project along with additional repairs associated with this summer’s storm damage. This project has been completed. If you have any questions or comments about the project, please contact the Engineering Department.

Project Description
This work involved the replacement of defective curbing, sidewalk and storm sewer catch basins in next year’s sealcoat area. The majority of the work this year is in the Lenox, Creekside and Brookside Neighborhoods.

Contact
Kyle Johnson | Engineering Project Manager
City Hall | 5005 Minnetonka Blvd. | St. Louis Park, MN 55416
P: (612) 756-4339 | kjohnson@stlouispark.org



Sanitary Sewer Rehabilitation - Regional (Metropolitan Council)

The Metropolitan Council is in the process of replacing and rehabilitating a regional sanitary sewer (force main) referred to as the Hopkins Interceptor. This sewer pipe extends across the entire length of the City of St. Louis Park from Hopkins to Minneapolis, and generally follows an alignment along the south frontage road of Highway 7, and Lake...


Water Tower No. 3 Re-Coating

updated: Monday, February 24, 2014

Current Status
This project has been completed. If you have any questions or comments about the project, please contact the Engineering Department.

Project Description
Water Tower No. 3, located in Elie Park, just off the intersection of 34 ½ Street and Wyoming Avenue. The project will include re-coating both the inside and outside surfaces of the tank, along with minor structural repairs and preparation prior to the actual coating work itself. Work is expected to be completed in October of 2013.

Resources
07-22-2013 Residential Notification Letter

Contact
Kyle Johnson | Engineering Project Manager
City Hall | 5005 Minnetonka Blvd. | St. Louis Park, MN 55416
P: (612) 756-4339 | kjohnson@stlouispark.org



Hennepin County Construction Projects

updated: Wednesday, February 12, 2014

Visit Hennepin County's website to learn about county roadway construction projects.



MnDOT Construction Projects

updated: Thursday, January 30, 2014

Visit the Minnesota Department of Transportation's website to learn about highway construction projects.



More Links

Engineering Department
5005 Minnetonka Blvd.
St. Louis Park, MN 55416
Phone: (952) 924-2656 Email: info@stlouispark.org