The Elmwood

Print
Press Enter to show all options, press Tab go to next option

the-elmwood

Latest construction update

April 2, 2019

  • Temporary earth retention walls have been completely installed
  • Approximately 70% of the concrete footings are installed, with concrete foundation pouring to begin the week of April 2, 2019
  • Precast plank installation is anticipated starting May 1, 2019
  • Rough carpentry framing is anticipated June 1, 2019

Visit www.elmwoodliving.com for more information on how to apply to live at The Elmwood.

Project background

36th Street LLC, the owner of the 36th Street Business Center/American Legion at 5605 W. 36th St., received approval for The Elmwood, a five-story, 70-unit, mixed-use development in October 2017. The approved development is located on a 0.99-acre parcel at the southeast corner of Xenwood Avenue and 36th Street West. The Elmwood consists of 53 market rate apartments with 17 affordable units at 60 percent area median income, and approximately 4,400 square feet of leasable office/commercial space. The development includes on-street, surface and underground parking, as well as outdoor amenity space.

Major amendment approval
  • The planning commission held a public hearing to gather comments and review the request for a major amendment to the development to reduce The Elmwood from six stories to five stories and from 85 units to 70 units. The commission voted 3 to 1 to recommend approval of the major amendment. 
  • City council approved the major planned unit development amendment ordinance on Oct. 2, 2017.
Original approval

The building was originally approved as a six-story, mixed-use building with 85 dwelling units in March 2017. Due to high construction costs, the applicant requested a major amendment to reduce the size of the development.

Resources and documents